8/8/2025 - PSE&G Gas Main Work - Week of 7/28 & 8/4 - updated

PSE&G has announced the schedule for Gas Main Replacement work on the below listed streets for next week:

Week of 7/28/2025 (GAS MAIN WORK)
Mon. 7/28  Hickory & Chestnut (Union towards Walnut) - MAIN CROSSINGS
Tues. 7/29: Laurel Street (Walnut & Spruce)
Wed. 7/30 - Thurs. 7/31: Laurel Street (Spruce & Cooper)
Fri. 8/1: No Work Scheduled

Week of 7/28/2025 (SERVICE WORK)
Mon 7/28 to Thurs. 7/31: Burlington Avenue (Edgewood to Willow) 
Fri. 8/1: No Work Scheduled

Week of 8/4/2025 (GAS MAIN WORK)
Mon. 8/4 - Tues. 8/5: Walnut (Pennsylvania & Laurel)
Wed. 8/6 to Thurs. 8/7: Spruce (Hickory & Pennsylvania)
Fri. 8/8: No Work Scheduled

Week of 8/4/2025 (SERVICE WORK)
Mon. 8/4 - Thurs. 8/7: Willow (Burlington to Second)
Fri. 8/8: No Work Scheduled

Please note this schedule is subject to change as conditions may warrant.