6/9/2025 - PSE&G Gas Main Work - Week of 6/9 & 6/16

PSE&G has announced the schedule for Gas Main Replacement work on the below listed streets for the next two weeks:

Week of 6/9/2025

Mon. 6/9 & Tues. 6/10 : Orchard Ave (from Walter to Second)

Wed. 6/11 through Fri. 6/13: Vine Street (from Burlington to Delaware/end of street)

Week of 6/16/2025

Mon. 6/16 & Tues. 6/17: Cedar Street (from Delaware to Third) and Third Street (from Cedar to Vine)

Wed. 6/18 through Fri. 6/20: Second Street (from dead end to Willow)

Please note this schedule is subject to change as conditions may warrant.

For more information about the Gas Main Replacement Project, please visit www.nj.pseg.com or click here for an informational video.